-----Original Message-----
From: Harold Cunliffe
Sent: Sunday, December 08, 2002 5:34 PM
To: Walda Lavroff; Ade Abon; Clair Muller; Gordon Certain; Howard Shook; John
C. Wilson; Justin Wiedeman; Katy Bryant; Lucy Smethurst; Mac Ryland; Mary
Norwood; Nancy Jones; Pat Gardner; Rick Daniel; Sally Mills; Sally Silver; Sy
Liebmann; 'Sylvia Bangle'; 'Bill Dreyfoos'; 'Carine'; 'Frederik'; 'Jeffrey
Groves - Brookhaven Assoc.'; 'Joan Smeltz'; 'Leah Knowlton'; 'Lisa Wargo -
Brookhaven Newsletter'; 'Matt Lawson'
Subject: Harold Cunliffe's 6th Report on Nancy Creek Tunnel
Dear All:
Pasted below and attached in Word for those of you who wish to edit, is my
6th Report. [The attachment was omitted from this web page.]
Harold Cunliffe
NANCY CREEK TUNNEL
Report as of December 6, 2002
This is the sixth Report on the above subject. Should you wish to receive the
first five, please e-mail me with your request. As before, I am reporting events
to the best of my recollection and I will try to differentiate when I am
offering an opinion. This Report may not be the position of the Technical
Advisory Committee nor the City of Atlanta.
The Technical Advisory Committee met on December 6, 2002 at the R. M. Clayton
plant (RMC) and toured the project site.
RM Clayton Site (NW Atlanta)
The Tunnel Contractor, Obayashi, has completed 14% of the project. The R. M.
Clayton Shaft has been excavated to a depth of 70 feet and concrete lined to 60
feet. Blasting has been required and so far, the shock waves have been lower
than initially thought. No complaints have been received. The Tunnel Boring
Machine (TBM) for the RMC segment is presently being rebuilt in Ohio. I was
impressed at the compactness of the RMC site. It occupies far less space than
its counterpart in Cobb. The contractor is also utilizing a large blasting mat
that fits over the top of the shaft. This undoubtedly is contributing to the low
impact of the blasting operation.
As a result of our Committee’s value engineering, the design team will
consolidate two of the RMC lift stations in the RMC shaft. This revision is
projected to save $10 - $15 million. Further, we will investigate the addition
of a low-head pump at RMC. This will cost $3,000,000 but will bring some relief
to homeowners on the lower stretches of the Nancy Creek in advance of the
completion of the Tunnel. Further, this addition may pay for itself in the short
term through energy savings.
Roswell Road Site (North Buckhead)
The Roswell [Road] site is being prepared. Pre-blast surveys within 1000 feet
of the Shaft are ongoing. The sound wall construction is underway. The Roswell
TBM is likewise being rebuilt. The Johnson Ferry site is still being planned and
will be discussed later in this report.
All easements that are on the critical path have been obtained. As of
December 2, 2002, 187 of the 320 required easements have been obtained.
Forty-nine are scheduled for condemnation. All storm water ponds have been
designed and all NPDES [National Pollutant Discharge Elimination System] Permits
have been obtained.
Johnson Ferry Road Site (DeKalb)
In a special session of the Committee, the current decision of the
construction of a Shaft at Johnson Ferry vs. a “shaftless” solution was
re-examined.
First, the decision to reject Obayashi’s bid of staging one TBM from
Johnson Ferry was discussed. This [previous decision] resulted in shifting
20,000 truckloads of excavation and 10 months of continuous operation from
Johnson Ferry to Roswell. In addition, the construction was extended 3 months
(perhaps resulting in 3 more months of downstream overflows) at an expense of
$1,400,000. Notwithstanding these impacts, our Technical Advisory Committee was
unanimous in its recommendation to reject Obayashi’s proposal because it did
not conform to the way that the project had been represented to the various
neighborhoods and, I believe, because of a sense the inequity involved in
shifting this impact from an Atlanta jurisdiction to a DeKalb jurisdiction.
Next, we discussed the “shaftless” option at Johnson Ferry. The
construction at Johnson Ferry is complicated by the requirement of two intake
shafts. These intakes receive flow from existing interceptor lines. The current
design contemplates that one of these intake shafts will be blasted underground
from the bottom of the shaft to the point of interception with the existing
sewer lines. With a shaftless solution, the construction of the intakes would
have to occur after the Tunnel is completed. Thus, the intake construction is
moved onto the critical path resulting in a 2 month extension to the
construction schedule. A vent shaft would now also have to be constructed at the
end of the tunneling operation adding a further month.
Next, logistical complications involving the TBM operation add another 1 ½
months. This includes pulling the TBM back to Roswell as opposed to lifting out
of the Johnson Ferry Shaft and having to run the TBM an extra 300 feet for
dismantling.
After the Tunnel is built, the concrete lining operation begins from Johnson
Ferry and proceeds to Roswell. But the lining will not completely fill all the
voids necessitating a “contact grouting” operation that commences as soon as
the concrete liner reaches a strength of 2,000 psi. With a shaft at Johnson
Ferry, the contact grouting can follow the lining operation but without a shaft,
it must be staged from Roswell and thus, must be delayed until the lining
operation clears Roswell. With the contact grouting now on the critical path, an
additional 2 months must be added to the construction schedule.
Our analysis resulted in a 6 ½ month extension to the construction period.
When asked to evaluate the same option, Obayashi speculated an additional 5
months would be required. Our Committee analysis indicated that an addition
$1,000,000 would be expended and Obayashi concluded, $2,500,000.
The construction schedule currently has a “float” of 2 months before the
penalties called for by the Consent Decree kick in. Once they do, the fine is
$1,000,000 plus $5,000 graduating to $8,500 per day. “Spending” these
additional two months at the initial stages of a project of this complexity
would be ill-advised. Non compliance with the Consent Decree would certainly
trigger a building moratorium. We did not attempt to calculate this cost.
Likewise, we did not attempt to calculate the cost to public health stemming
from additional overflows.
Many of these logistical concerns are brought about by the decision to
construct one of the intake shafts utilizing an underground operation. The
design team decided on this approach because of the impact of an “open cut”
operation that must cross Nancy Creek and its environs. By employing the “open
cut” method, it is believed that the Johnson Ferry Shaft could be reduced to
15 or 16 feet in diameter and that a potential savings of $1,000,000 could be
realized with little impact on the schedule. In my opinion, the reduction in
shaft size would result in a marginal decrease in construction impact at the
shaft, but the open cut operation in Nancy Creek would be highly undesirable and
remembered for years.
Nevertheless, the construction manager was asked to discuss this option with
Obayashi. They were also asked to independently evaluate the construction
schedule that would result from a shaftless and from a reduced shaft size at
Johnson Ferry for our next meeting.
The option of shifting either a shaft or a shaftless termination point to
Evergreen was briefly discussed. As discussed in previous reports, this would
involve a realignment of the Tunnel into a zone of unstable rock thus greatly
increasing the chance of ground water infiltration and / or the costs of
mitigation of infiltration. It would also be located in a heavily treed area.
Further during the early stages of design, Dekalb County indicated a preference
of having the Tunnel terminate within Dekalb County.
Again, no Frequently Asked Questions were asked of me.