CREEK TUNNEL
Report as of
January 10, 2003
This
is the seventh Report on the above subject. Should you wish to receive the first
six, please e-mail me with your request. As before, I
am reporting events to the best of my recollection and I will try to
differentiate when I am offering an opinion. This Report may not be the position
of the Technical Advisory Committee nor the City of
Atlanta
.
The
Technical Advisory Committee met on
January 10, 2003
at the R. M. Clayton plant (RMC).
RM Clayton Site (NW Atlanta)
The
Tunnel Contractor, Obayashi, has completed 16% of the project. The R. M. Clayton
Shaft has been excavated to a depth of 110 feet and concrete lined to 100 feet.
While we were meeting, Obayashi blasted another layer about 500 feet from us. It
sounded like a freight train passing for about 2 seconds. I could not detect any
movement.
Roswell Road Site (North Buckhead)
The
sound wall at the Roswell
site is being completed. The pre-blast video surveys within 1000 feet of the
Shaft are ongoing. All requests to enter property to conduct these surveys have
been made. Strangely, several property owners have waived their rights to this
survey. The City has decided that anyone along the Tunnel alignment can have the
pre-construction video survey conducted even if they have previously declined or
if they are outside the 1000 foot radius of influence. Call Mike Robinson at 404
352-0701 to arrange this service. The Cat Doctor building will soon be
demolished. They are now located at 4716 Roswell Road – 3/10 mile north of
Windsor on the west side of Roswell Road.
Johnson Ferry Road Site (DeKalb)
Site
acquisition and negotiations are ongoing at Johnson Ferry.
Since
no Frequently Asked Questions were presented, my report is concluded.